How long does an apartment renovation take?

Cosmetic renovation of a 1-bedroom (35–45 m²): 3–5 weeks. Cosmetic renovation of a 2-bedroom (55–65 m²): 5–7 weeks. Major renovation of a 1-bedroom: 2–3 months. Major renovation of a 2-bedroom with layout changes: 4–6 months. Main delay causes: material deliveries (allow 2–3 weeks buffer), screed curing (28 days before parquet), and downtime from poor coordination between sub-trades. Fix each phase deadline in the contract with delay penalties.