What is the correct order of renovation works?

Correct order: 1) Demolition (partition removal, old finishes, window replacement); 2) Rough work (routing utilities — pipes, wiring, ventilation); 3) Floor screed (28 days curing); 4) Wall leveling (plastering, 14–21 days); 5) Ceiling and wall skimming; 6) Door installation; 7) Tile installation; 8) Final wall finish (wallpaper, painting); 9) Laminate/parquet installation; 10) Baseboards, outlets, light fixtures. Skipping this order is the main reason for rework.