How long does renovation take: realistic timeline guide

Most renovation delays do not come from the contractor working slowly. They come from late material deliveries, undiscovered defects and decisions that were not made before work started.

Typical durations by room and scope

A cosmetic refresh of one room takes 3–5 days. A full bathroom renovation takes 3–5 weeks. A full apartment overhaul of 60 sqm typically takes 2–4 months. Add 20–30 % buffer for first-time renovations.

The three biggest delay causes

First: materials ordered late or delivered to wrong spec. Second: hidden defects found after demolition — rotten subfloor, old wiring behind tiles, wet walls. Third: design decisions changed mid-work.

How to compress the timeline

Order all materials before work starts, not after. Decide on tile, flooring, fixtures and paint colors in advance. Keep one person as the single decision-maker on site to avoid approval loops.

Useful next steps

  • Materials ordered before work starts
  • Design decisions finalized
  • Buffer of 25% added to timeline
  • Single decision-maker named
  • Demolition findings reviewed before next phase