How much budget reserve should you plan for renovation?

Standard reserve: 15–20% of the estimate. For older buildings (pre-1980): 25–30% — hidden surprises (rotten floor joists, hidden wiring, Soviet-era screed) are more common. Typical unexpected costs: replacing a hidden corroded pipe — €500–2,000; fixing severely uneven walls — €200–800/room; rush delivery of matching materials — 20–40% surcharge. Rule: the reserve stays with you and is spent only when the scope genuinely changes — it's not a bonus for the contractor.